Greystones Sewerage Scheme

Client: Wicklow County Council
Project Value: Capital Value €18 Mllion (WWTP & Collection Network)
€1,500,000 Mllion (proposed advanced sludge treatment) Estimated Annual Operating Cost (2003 Prices) – € 1,000,000
Services Provided: Environmental Impact Assessment, Preliminary & Detailed Design, Project Management, Construction Supervision and Contract Documentation for the Engagement of 20 yr DBO Contractor

Key Features:
The project comprises the provision of a 40,000 PE waste water treatment plant and associated upgrades of the collection network.

The collection network upgrades includes the provision of 2 new outlying pumping stations and the provision of an additional 12km of sewers ranging from 300 to 1200mm in diameter.

The waste water treatment plant process comprises preliminary treatment (screening, degritting and storm water handling), followed by primary sedimentation and an activated sludge process, resulting in a final effluent standard of 25 mg/l BOD and 35 mg/l suspended solids. The discharges from the plant are via separate storm and final effluent marine outfalls.

The sludge treatment process comprises anaerobic digestion, with biogas utilisation and dewatering.